Seawall Update

  1. Sewall request to DEQ required an adjustment after being originally processed. The Adjustment increased the size of the project from small to a medium seawall project after the onsite review in November.
  2. Public Notice was published in December by the DEQ. Public notice is open for up to 90 days. The decision is expected in the near future.
  3. West Bloomfield Permit paperwork is ready to be submitted by American Marine upon DEQ approval.
  4. CEBIA was slated to be the first job for American Marine, but the change of job classification has presented a few month delay. We are in the work plan for 2015.
  5. Regular updates will occur on this project, as the milestones are achieved.

Please contact Jared Hartz with question on this topic.